The Partial Redevelopment Project was initiated by former school supervisor Mrs. Lucy LAU CHAN So May and former principal Mrs. WONG SZE Lo Sai in 2007. After extensive preliminary discussions with the Education Bureau by former principal Mr. WONG Ming Hau and former vice-principal Mr. YIU Che Keung, consensus was reached in 2012. A technical feasibility study was made by the school and was approved by the Education Bureau in 2013. Consultants for architectural services and quantity surveying were recruited to follow the project since 2015. With the assistance of honorary advisor, Ms. Anna KWONG, the design of the new campus was finalized and approved by the Education Bureau and the Architectural Services Department. In 2019 and 2020, the project was discussed and approved by the Eastern District Council, Panel on Education, Public Works Subcommittee and Finance Committee of the Legislative Council. HK$285 million will be subvented by the government for the project. The construction works commenced in December 2021 and are projected to be completed in the first quarter of 2025.
始自2007年,前任校監劉陳素薇女士和時任校長黃施露茜女士已向當時的教育統籌局申請擴建校舍,及後,經前任校長黃明孝先生和時任副校長姚志強先生與局方多年的磋商,終於在2012年達成初步共識,學校亦於2013年向教育局提交可行性研究報告,並獲當局通過。於2015年,學校聘請了建築工程顧問及工料測量顧問負責擴建工程計劃。在榮譽顧問鄺心怡建築師的協助下,工程設計獲教育局及建築署的批准。於2019及2020年,重建計劃經東區區議會、立法會工務小組及立法會財務委員會討論及通過,並獲政府撥款2億8仟多萬元資助進行工程。工程已於2021年12月展開,預計在2025年的第一季竣工。
2007
Jun 6月
Request to Education and Manpower Bureau for upgrading of school facilities
向教育統籌局申請擴建校舍
2013
Sep 9月
Technical Feasibility Study approved by EDB
可行性研究報告獲教育局批准
Oct 10月
Project upgraded to Category B-
計劃獲提升至B- 級別
Nov 11月
Alumnus Ms. Joanne WONG assisted the school to process the tenders for AACS and QS consultancy services.
獲黃安萍校友協助進行兩個顧問的招標
2015
Feb 2月
AACS and QS Consultants engaged
聘用建築工程顧問及工料測量顧問
Nov 11月
Ground investigation
進行地質測量
2017
Oct 10月
Project upgraded to Category B+
計劃獲提升至B+ 級別
2019
Jun 6月
Project approved by Eastern District Council Planning, Works and Housing Committee
獲東區區議會規劃工程及房屋事務委員會討論及通過
2020
Jan 1月
Project approved by Panel on Education of the Legislative Council
獲立法會教育事務委員會討論及通過
Jun 6月
Project approved by Public Works Subcommittee of the Legislative Council
獲立法會財務委員會工務
小組委員會討論及通過
Jul 7月
Project approved by Finance Committee of the Legislative Council
獲立法會財務委員會通過撥款
Project upgraded to Category A
計劃獲提升至A 級別
2021
Dec 12月
Main works contractor approved by EDB
獲教育局通過聘任建築工程承建商
Commencement of construction works
工程展開
2025
Mar 3月
(Projected 預計)Completion of construction works
預計竣工日期